LNG Jetty Expansion FEED activities carried with below scope of work
- Mooring Analysis as per OCIMF Guidelines for 180k m3 LNG Carrier
- Design of Mooring Pile and Driveability Analysis
- New 30m Catwalk Design
- New Fender, Anode Selection Study
- MTO Report
- Basis for Design Report
- Construction Methodology
- Crane Operation Feasibility Checks
- Cargo Barge Loading Layouts
- Installation Vessel Positioning Layouts.